ON going projects

Pavimental is currently working on the expansion of over 130 km of carriageway on the A/9 (Lainate – Como - Chiasso), on the A/14 (the North Rimini – Cattolica; Fano – Senigallia and North Rimini - Pedaso sections) and on the A/1 (Barberino di Mugello - Incisa Valdarno and North Florence- South Florence sections). Works are also underway to build or replace safety and noise barriers along numerous sections of the motorway network. Pavimental is also starting work on the construction of interchanges Genova San Benigno, Crespellano and industrial area of Foggia and those related to Rho-Monza. The total amount of the works exceeds EUR 1,350 million. Leggi altro

Rebuilding of the viaduct connecting the A1…

The rebuilding of the Lepido viaduct at Borgo Panigale completed in only 53 days.  The works, which started the day after the collapse of a span of the overpass caused by an accident in which a tanker exploded, were initially expected to take 5…

Via della Superba - Genoa

Road reserved for heavy vehicles heading to the port of Genoa opened on 19 September 2018   Length: 3.7 km Duration of the work: 27 consecutive days (22 August to 18 September 2018) Workforce used: 50 resources Quantity of bituminous…

LOTTO 3: Variante di Baranzate

Viabilità di adduzione al sistema autostradale esistente A8/A52   Valore del progetto: Euro 102.336.563,53 lordi Inizio lavori: 02/04/2014 da primo verbale di consegna provvisorio Durata lavori prevista: 885 giorni…

A1 MILAN – NAPLES MOTORWAY WORKS ON…

Project value: Euro 31,010,798.86   Start of works: 2015, October   End of works: 2017, May   Expected duration of works: 570 days   Earth movements: 231,052 m3   Sub-foundations: 47,308 m3   Concrete:…

A1 Milan – Naples. Construction of the…

The project constitutes a small part of the construction of the third lane of the A1 Milan – Naples motorway, on the stretch from Florence South to Incisa. The construction project is aimed at bringing the existing infrastructure to a…

G. B. Pastine Airport - Ciampino - Structural…

Project value: Euro 8.636.502,78 Start of works: 2016, August 12 End of works: 2017, April 9   Expected duration of works: 240 days – 3 phases Earth movements: 82,000 m3 Sub-foundations:38,500 m3 Asphalt surfacing: 45,000 TONNES…

Barberino di Mugello – Firenze Incisa…

Project value: 223.454.548,18 Euros End of works (as per contract): 2018, November Start of works: 2014, May 22nd Expected duration of works: 1.643 days   Earth movements: 1.979.315,29 M3 Sub-foundations: 8.961,83 M3 - 7.436,00…

Certifications

Pavimental considers Safety, Environment and Quality to be strategic factors that also provide a competitive edge. The key role assigned to these three areas takes the form of a continuous commitment to search for new eco-compatible materials and develop technologies for the recovery and reuse of products used, on the one hand, and, on the other, the certification of all aspects relating to its business, which are often one step ahead of and go well beyond simply compliance with legal obligations. Leggi altro